The Federal Energy Regulatory Commission (FERC) rejected an effort Friday to allow an Amazon data center to ... power plant were necessary. The regulator’s two Republican commissioners ...
Talen Energy Corp. says Amazon has planned up to 960 ... But the energy regulator's commissioners voted 2-1 to reject the deal, finding that the applicants “failed to meet the high burden ...
Talen Energy has asked federal regulators to rehear its rejected agreement to ramp up power to an Amazon data center located ...